Progress report on student hostels development

Theresa Fox

 

Dr Brian Mitchenere has crossed his fingers many times that a project will be finished on time and according to plan. So the Associate Director of Campus Planning can be excused for having his fingers and toes crossed these days, as the official completion date for Blocks I and II of Phase I of the student hostels project draws near. "The scaffolding is coming down and we're doing all we can to press the builder to be finished on time. But there's a saying in this business that with building contracts, if anything can go wrong, it always does."

The official completion date is 14 April, as the contractors were given extra time because of inclement weather. The Campus Planning Office (CPO) expects Blocks I and II to be completed by the end of April and Block III, which includes the multi-function hall, around the end of May, Dr Mitchenere said.

With the scaffolding coming down, work is progressing on the inside of the buildings. Already, much of the plastering work is completed, the lifts are installed, though not commissioned, and the internal finishing and building services are well under way. "The mock-up for the typical student room has been finished, including the soft furnishing--as has the mock-up of one of the flats in the essential staff quarters," Dr Mitchenere reported.

CPO is hoping to have all the soft furnishing installed by mid-June, which will give CityU staff time to familiarize themselves with the new buildings before the initial influx of students. A group of undergraduate students from Shanghai will be the first to experience hostel life on the CityU campus. They will move in at the beginning of August, followed by our own students at the end of August, in time for the new semester in September.

As for the later phases, Phase II suffered a setback when the contractor filed for court protection in Japan. This had a knock-on effect and worked stopped on the CityU site. The project has been re-tendered and CPO expects work will re-commence on site in early March and that Phase II will be completed by the original date of August 2003.
Tender documentation for Phase III is currently being compiled and the aim is to go to tender for that phase in March, Dr Mitchenere said.

For a live view of what's happening on Phase I, log on to www.pd4n48r.xyz/cityu/about/view.htm.

 

你可能感興趣

聯(lián)絡(luò)資料

傳訊及數(shù)據(jù)研究處

Back to top
澳门百家乐心得玩博| 六合彩即时开奖| 百家乐官网算号软件| 巴黎人百家乐官网的玩法技巧和规则| 百家乐电子游戏试| 丰禾国际| 百家乐官网技巧开户| bet365存| 百家乐北京| 百家乐官网庄闲对冲| 百家乐专家赢钱打法| 平南县| 百家乐官网威尼斯人| 百家乐平预测软件| 百家乐官网赌场代理| 金博士娱乐城优惠| 百家乐平台在线| 南宁百家乐官网赌机| 香港六合彩公司| 百家乐tie| 百家乐官网7赢6| bet365备用网址器| 百家乐赌王有哪些| 百家乐官网赢家打法| 百家娱乐| 竞咪百家乐官网的玩法技巧和规则 | 2024年九宫八卦吉位| 足球投注网站| 澳门百家乐娱乐城送彩金| 百家乐官网白菜价| 皇冠平台| 北京德州扑克比赛| 线上百家乐官网平台| 真人娱乐场| 金榜百家乐官网的玩法技巧和规则| 扶沟县| ,| 百家乐77scs| 百家乐大西洋城| 澳门百家乐赌客| 现金百家乐|