Progress report on student hostels development

Theresa Fox

 

Dr Brian Mitchenere has crossed his fingers many times that a project will be finished on time and according to plan. So the Associate Director of Campus Planning can be excused for having his fingers and toes crossed these days, as the official completion date for Blocks I and II of Phase I of the student hostels project draws near. "The scaffolding is coming down and we're doing all we can to press the builder to be finished on time. But there's a saying in this business that with building contracts, if anything can go wrong, it always does."

The official completion date is 14 April, as the contractors were given extra time because of inclement weather. The Campus Planning Office (CPO) expects Blocks I and II to be completed by the end of April and Block III, which includes the multi-function hall, around the end of May, Dr Mitchenere said.

With the scaffolding coming down, work is progressing on the inside of the buildings. Already, much of the plastering work is completed, the lifts are installed, though not commissioned, and the internal finishing and building services are well under way. "The mock-up for the typical student room has been finished, including the soft furnishing--as has the mock-up of one of the flats in the essential staff quarters," Dr Mitchenere reported.

CPO is hoping to have all the soft furnishing installed by mid-June, which will give CityU staff time to familiarize themselves with the new buildings before the initial influx of students. A group of undergraduate students from Shanghai will be the first to experience hostel life on the CityU campus. They will move in at the beginning of August, followed by our own students at the end of August, in time for the new semester in September.

As for the later phases, Phase II suffered a setback when the contractor filed for court protection in Japan. This had a knock-on effect and worked stopped on the CityU site. The project has been re-tendered and CPO expects work will re-commence on site in early March and that Phase II will be completed by the original date of August 2003.
Tender documentation for Phase III is currently being compiled and the aim is to go to tender for that phase in March, Dr Mitchenere said.

For a live view of what's happening on Phase I, log on to www.pd4n48r.xyz/cityu/about/view.htm.

 

你可能感興趣

聯(lián)絡(luò)資料

傳訊及數(shù)據(jù)研究處

Back to top
全讯网找新全讯网| 六合彩开奖时间| 百家乐为什么庄5| 大发888 游戏下载| 百家乐官网缩水| 17pk棋牌官方下载| bet365代理| 广州百家乐官网赌城| 万豪国际| 百家乐两边| 视频百家乐官网平台出租| 玩百家乐如何看路| 棋牌网站| 济州岛百家乐的玩法技巧和规则| 百家乐官网换人| 鸿宝娱乐| 网上百家乐赌博犯法吗| 至尊百家乐官网娱乐场开户注册 | 24山吉凶八卦图| 玩百家乐官网游戏经验| 二八杠下载| 百家乐开户首选| 澳门百家乐官网网上赌城| 赌场风云下载| 大发888娱乐城官方下载lm0| 百家乐代理商博彩e族| 澳门百家乐官网骗人| 威尼斯人娱乐场 新世纪| 皇冠百家乐的玩法技巧和规则| 百家乐游戏机高手| 百家乐官网麻将牌| 澳门百家乐官网网上娱乐场开户注册| 百家乐官网牌数计算法| 深圳百家乐的玩法技巧和规则| 百家乐的保单打法| 百家乐官网投法| 澳门百家乐官网线上娱乐城| 大发888在线体育官网| 棋牌百家乐有稳赚的方法吗| 一直对百家乐官网很感兴趣.zibo太阳城娱乐城 | 环球百家乐官网娱乐城|